Class: SSS 3
Term: Second Term
Subject: Building Construction
Time: 2 Hours 30 Minutes
Total Marks: 70
SECTION A: OBJECTIVES (40 Marks)
Instruction: Answer ALL 40 questions. Each question carries 1 mark.
- The correct step before using locally produced fired-clay bricks in an external wall is to ________. (a) assume all bricks fired anywhere have identical properties (b) substitute wall paint for strength assessment (c) ignore bonding because units are locally made (d) check dimensions, strength, absorption and conformity to the specified use
- A proposed access road follows a low-lying path where runoff collects after rainfall. The design should prioritise ________. (a) surface drainage and stable formation before laying the final course (b) decorative paint before soil assessment (c) a level cross-section with no outlet (d) uncompacted fill directly below the running surface
- Which of the following best differentiates rigid and flexible road pavements? (a) Rigid pavements require no supporting ground (b) Flexible pavements have no foundation layers (c) Rigid pavements must always be narrower than flexible ones (d) Rigid pavements rely significantly on slab action; flexible pavements distribute load through layered materials
- The main reason the location of buried services matters before planting trees is to ________. (a) avoid future root conflicts and damage during excavation or maintenance (b) guarantee every root stays above ground (c) remove the need for service drawings (d) make paved paths self-cleaning
- Which proposed selection method does NOT support reliable construction quality? (a) Testing representative samples (b) Confirming suitability for moisture exposure (c) Choosing solely by price without confirming intended structural or durability performance (d) Comparing quantities and transport constraints
- Which of the following is the strongest reason to include planting and shade in a compound design? (a) All plants eliminate the need for storm-water management (b) Tree roots always strengthen every nearby foundation (c) Planting automatically removes maintenance requirements (d) They can improve outdoor comfort, appearance and site use when appropriately located
- The main reason road subgrade needs inspection before pavement construction is to ________. (a) select the final surface colour (b) determine the size of road nameplates (c) confirm support and moisture conditions affecting long-term deformation (d) replace any need for materials testing
- Which of the following most directly reduces erosion where a road cuts across sloping ground? (a) Well-directed drainage with appropriate stabilisation of exposed slopes (b) Concentrating runoff onto unprotected soil (c) Removing all vegetation without surface protection (d) Placing a decorative kerb without considering water flow
- Which of the following is a credible way to encourage appropriate adoption of local materials? (a) Mandatory replacement of all conventional products regardless of use (b) Clear specifications, training and evidence of satisfactory field performance (c) Prohibiting inspection of manufacturing practices (d) Ignoring client safety concerns
- The correct step before compacting a new access-road layer is to ________. (a) apply the road-marking paint to the exposed soil (b) start traffic loading before layer preparation (c) confirm material type, appropriate thickness and moisture condition (d) mix uncontrolled organic debris into the fill
- The ________ of a landscaped slope affects both erosion risk and the choice of planting or retaining measures. (a) paint thickness (b) electrical frequency (c) roof span (d) gradient
- Which of the following best explains why local building materials may be economically attractive? (a) Local materials never require processing or testing (b) Shorter transport distances and local availability may lower some costs (c) Every local source has unlimited supply (d) The price of labour and transport can be ignored
- A newly landscaped slope shows exposed soil washed into a drain. The most appropriate intervention is ________. (a) keep clearing the drain without addressing slope erosion (b) increase the volume of uncontrolled surface discharge (c) improve surface stabilisation and runoff management together (d) remove every outlet at the foot of the slope
- A builder substitutes untreated weak earth blocks for specified load-bearing units. The main concern is ________. (a) an automatic increase in design capacity (b) inadequate strength and durability relative to structural and environmental demands (c) guaranteed resistance to wetting (d) complete elimination of construction tolerances
- Which of the following best explains why landscaping should be coordinated with access-road design? (a) Landscape features can be set out without site measurements (b) Road entrances should always cross protected planting beds (c) Planting, pedestrian paths, vehicle movement and drainage share limited site space (d) Planting eliminates the need to consider road visibility
- Repeated rutting appears soon after a lightly trafficked access road opens. A useful technical diagnosis is ________. (a) excessive strength of properly prepared subgrade (b) insufficient compaction or weak saturated support below the surfacing (c) overly regular crossfall (d) incorrect advertising of the road project
- A firm plans to market a new building panel as a replacement for masonry. The sound technical approach is ________. (a) evaluate its structural, moisture, thermal and installation performance before adoption (b) use only a publicity photograph as proof of adequacy (c) assume mass production guarantees fire performance (d) remove design calculations from the approval process
- The correct step before grading a landscaped court near a building is to ________. (a) grade solely by visual impression after paving (b) block all planned drains (c) lower the ground to bridge the building’s damp-proof course (d) establish finished levels that direct surface water safely away from vulnerable areas
- A proposed locally produced masonry unit meets compressive strength but performs poorly under water exposure. The specification should ________. (a) consider exposure conditions and additional durability measures before approval (b) approve it for all external uses without modification (c) assume strength alone settles every material property (d) discard all testing records after a single trial
- The ________ of locally sourced material should be evaluated against design requirements, not assumed from geographic proximity. (a) advertising reach (b) fitness for purpose (c) colour alone (d) supply slogan
- Which proposal does NOT account for predictable rainfall on an access road? (a) A low point without drainage outlet or allowance for ponding (b) Side drains or other suitable run-off paths (c) Appropriate crossfall (d) Protection of road edges against erosion
- The ________ provides a prepared support layer immediately beneath specified road surfacing in many pavement designs. (a) gutter outlet (b) roof purlin (c) base course (d) wall lintel
- Which of these is not a normal material or feature in an external landscape design? (a) An unconnected electrical cable disguised as a planting stake (b) Paving units (c) Topsoil (d) Shrubs or ground cover
- The soundest comparison between two candidate materials for access-road construction is based on ________. (a) purchase price alone (b) their names on the delivery docket (c) performance requirements, whole-life costs and environmental exposure (d) which supplier has the largest banner
- A school wants an outdoor seating area but cannot afford high-maintenance planting. The most sensible principle is ________. (a) choose durable features and planting suited to realistic maintenance capacity (b) select the most water-dependent plants regardless of supply (c) omit safe access because the area is decorative (d) ignore expected foot traffic
- All these support a sustainable landscape plan EXCEPT ________. (a) suitable species selection (b) planned watering and maintenance (c) placing large-rooted trees directly against vulnerable underground services without assessment (d) protection of drainage routes
- An access road enters a compound at a sharp turn used by delivery vehicles. A design revision should examine ________. (a) the colour of the vehicles’ registration plates (b) whether a wider gate alone solves every turning constraint (c) increasing obstruction at the inside corner (d) swept-path clearance and safe turning geometry
- ________ is the planned arrangement of landform, vegetation and built outdoor features to improve a site’s use and appearance. (a) Prestressing (b) Borehole drilling (c) Landscaping (d) Reinforcement bending
- Which of these is not an example of a locally sourced building material? (a) Locally quarried stone (b) A software licence governing a contractor’s CAD tool (c) Timber obtained from an appropriate local supplier (d) Locally produced clay bricks
- A pavement contractor proposes a different locally available stone for the base. The best response is ________. (a) test its grading, strength and suitability for the designed layer before approval (b) approve it solely because it is cheaper (c) assume every rock material behaves identically (d) replace compaction tests with supplier photographs
- A cheap local timber has high moisture content before use in joinery. The relevant quality risk is ________. (a) automatic immunity to fungi (b) increased dimensional stability under all conditions (c) movement, distortion or biological deterioration if not properly treated or seasoned (d) complete avoidance of shrinkage
- All these help an access road remain serviceable EXCEPT ________. (a) adequate grading (b) placing surfacing on soft fill without compaction or drainage (c) suitable load-bearing layers (d) effective roadside drainage
- Which action does NOT follow sound landscape installation procedure? (a) Preparing the planting area (b) Positioning plants to suit site conditions (c) Providing for maintenance and watering (d) Planting without considering soil, access, drainage or service routes
- The main reason earthen building materials may require stabilisation or protection is to ________. (a) make unit geometry irrelevant (b) improve performance against moisture and strength-related limitations where needed (c) guarantee they carry any load without testing (d) remove the need for correct workmanship
- Which of these is not ordinarily a measure of access-road quality? (a) Evenness of the riding surface (b) Provision for surface drainage (c) Resistance to rutting and traffic damage (d) The number of promotional posters printed for contractors
- A garden path becomes slippery during the rainy season. The design should reassess ________. (a) surface texture, water discharge and ease of maintenance (b) only the colour of its adjacent flower beds (c) the wall’s electrical socket rating (d) whether the site entrance can be painted again
- ________ is a soil material commonly used for building or road works in parts of Nigeria, subject to appropriate assessment and treatment. (a) Roof flashing (b) Silicone sealant (c) Unfired cement paste (d) Laterite
- All these may limit wider adoption of locally sourced materials EXCEPT ________. (a) variable supply quality (b) consistent quality control and documented satisfactory performance (c) limited processing or standardisation (d) poor public confidence in performance
- ________ is the transverse slope formed on a road surface to assist drainage towards the edges. (a) Superelevation around every straight section (b) Gradient along a vertical wall (c) Bearing capacity (d) Camber
- An attractive new planting bed blocks a building’s existing surface drain. The most serious design fault is ________. (a) the plant spacing is necessarily too wide (b) beautification has compromised effective drainage and building protection (c) plant growth will immediately end all rainfall (d) the project uses more than one planting species
SECTION B: THEORY (30 Marks)
Instruction: Answer Question 1 and any other TWO questions. Each question carries 10 marks.
1. Answer the following questions.
(a) A school access road develops potholes and rutting after heavy rain. Identify five design or construction weaknesses that could explain the failure. (5 marks)
(b) Explain five checks needed before approving a substitute locally available material for the road base. (5 marks)
2. Answer the following questions.
(a) A new landscaping plan includes a car park, shaded paths and an ornamental slope adjacent to a building. Evaluate five site-planning decisions that should be coordinated. (5 marks)
(b) Suggest five responses when surface runoff from a newly landscaped area erodes soil and blocks the compound drains. (5 marks)
3. Answer the following questions.
(a) A builder wants to use locally produced bricks and timber instead of imported products. Explain five quality and procurement considerations. (5 marks)
(b) Compare five benefits and limitations of sourcing construction materials locally. (5 marks)
4. Answer the following questions.
(a) An access road and adjoining landscape cross a sloping site with high seasonal rainfall. Outline five coordinated construction measures to control water and erosion. (5 marks)
(b) A client proposes a new locally manufactured wall panel. Describe five tests or information items needed to judge its suitability for a small building. (5 marks)
OBJECTIVE MARKING SCHEME
Question 1 – ✅ (d) check dimensions, strength, absorption and conformity to the specified use
Question 2 – ✅ (a) surface drainage and stable formation before laying the final course
Question 3 – ✅ (d) Rigid pavements rely significantly on slab action; flexible pavements distribute load through layered materials
Question 4 – ✅ (a) avoid future root conflicts and damage during excavation or maintenance
Question 5 – ✅ (c) Choosing solely by price without confirming intended structural or durability performance
Question 6 – ✅ (d) They can improve outdoor comfort, appearance and site use when appropriately located
Question 7 – ✅ (c) confirm support and moisture conditions affecting long-term deformation
Question 8 – ✅ (a) Well-directed drainage with appropriate stabilisation of exposed slopes
Question 9 – ✅ (b) Clear specifications, training and evidence of satisfactory field performance
Question 10 – ✅ (c) confirm material type, appropriate thickness and moisture condition
Question 11 – ✅ (d) gradient
Question 12 – ✅ (b) Shorter transport distances and local availability may lower some costs
Question 13 – ✅ (c) improve surface stabilisation and runoff management together
Question 14 – ✅ (b) inadequate strength and durability relative to structural and environmental demands
Question 15 – ✅ (c) Planting, pedestrian paths, vehicle movement and drainage share limited site space
Question 16 – ✅ (b) insufficient compaction or weak saturated support below the surfacing
Question 17 – ✅ (a) evaluate its structural, moisture, thermal and installation performance before adoption
Question 18 – ✅ (d) establish finished levels that direct surface water safely away from vulnerable areas
Question 19 – ✅ (a) consider exposure conditions and additional durability measures before approval
Question 20 – ✅ (b) fitness for purpose
Question 21 – ✅ (a) A low point without drainage outlet or allowance for ponding
Question 22 – ✅ (c) base course
Question 23 – ✅ (a) An unconnected electrical cable disguised as a planting stake
Question 24 – ✅ (c) performance requirements, whole-life costs and environmental exposure
Question 25 – ✅ (a) choose durable features and planting suited to realistic maintenance capacity
Question 26 – ✅ (c) placing large-rooted trees directly against vulnerable underground services without assessment
Question 27 – ✅ (d) swept-path clearance and safe turning geometry
Question 28 – ✅ (c) Landscaping
Question 29 – ✅ (b) A software licence governing a contractor’s CAD tool
Question 30 – ✅ (a) test its grading, strength and suitability for the designed layer before approval
Question 31 – ✅ (c) movement, distortion or biological deterioration if not properly treated or seasoned
Question 32 – ✅ (b) placing surfacing on soft fill without compaction or drainage
Question 33 – ✅ (d) Planting without considering soil, access, drainage or service routes
Question 34 – ✅ (b) improve performance against moisture and strength-related limitations where needed
Question 35 – ✅ (d) The number of promotional posters printed for contractors
Question 36 – ✅ (a) surface texture, water discharge and ease of maintenance
Question 37 – ✅ (d) Laterite
Question 38 – ✅ (b) consistent quality control and documented satisfactory performance
Question 39 – ✅ (d) Camber
Question 40 – ✅ (b) beautification has compromised effective drainage and building protection
THEORY MARKING SCHEME (Answer 3 × 10 = 30 Marks)
Question 1 (10 Marks)
(a) 5 marks: Poor drainage (1); weak formation/subgrade (1); inadequate compaction (1); unsuitable layer materials/thickness (1); excessive or poorly assessed traffic load (1).
(b) 5 marks: Material grading (1); strength/quality tests (1); moisture/drainage susceptibility (1); compaction suitability (1); comparison with specification and load demand (1).
Question 2 (10 Marks)
(a) 5 marks: Vehicle/pedestrian circulation (1); service routes (1); tree roots and shade (1); grading/drainage (1); slope stabilisation/maintenance (1).
(b) 5 marks: Intercept water (1); provide suitable outlets (1); protect bare soil (1); stabilise slope/plant cover (1); maintain and inspect drains (1).
Question 3 (10 Marks)
(a) 5 marks: Verified strength/durability (1); moisture/seasoning or absorption (1); dimensional consistency (1); cost and supply reliability (1); conformity with construction specification (1).
(b) 5 marks: Transport-cost advantage (1); local enterprise benefits (1); availability/lead times (1); quality variability (1); need for testing or processing (1).
Question 4 (10 Marks)
(a) 5 marks: Crossfall/camber (1); side drains and outlets (1); stable road layers/compaction (1); slope vegetation or protection (1); serviceable inspection/maintenance (1).
(b) 5 marks: Strength and loading (1); moisture resistance (1); durability and weathering (1); fixing and installation (1); availability/cost and documented compliance (1).