Class: SSS 3
Term: First Term
Subject: Block Laying and Brick Laying
Time: 2 Hours 30 Minutes
Total Marks: 70
SECTION A: OBJECTIVES (40 Marks)
Instruction: Answer ALL 40 questions. Each question carries 1 mark.
- Which of the following best distinguishes prestressed concrete from ordinary reinforced concrete? (a) Steel is always absent from the member (b) Prestressed members cannot carry bending loads (c) Concrete is poured without any quality control (d) Internal compression is deliberately introduced before or during service to counter tensile effects
- The correct step when a foundation excavation exposes unexpectedly soft ground is to ________. (a) increase roof loads to compact the soil quickly (b) cover the excavation with tiles and continue (c) seek reassessment of the founding conditions before proceeding (d) cast the foundation without considering bearing behaviour
- The main reason brick or block joints are staggered is to ________. (a) distribute loads and avoid continuous planes of weakness (b) replace the need for any horizontal support (c) make every wall independent of a foundation (d) prevent cement from setting
- Which of the following would most directly undermine a wall’s bond and stability? (a) Proper overlap between adjacent courses (b) Continuous aligned vertical joints through several courses (c) Uniformly filled mortar joints (d) A plumb, properly aligned wall face
- The main reason prestressing can permit longer structural spans is that ________. (a) it eliminates every possible form of deflection (b) cement no longer needs time to gain strength (c) introduced compression helps resist service-induced tension and cracking (d) the steel has no interaction with the concrete
- A tile schedule for a wall measuring 5 m × 3 m, with no openings, should start from a gross area of ________. (a) 15 m² (b) 8 m² (c) 30 m² (d) 45 m²
- The ________ of freshly cast concrete helps maintain moisture and temperature conditions needed for strength development. (a) dry rubbing (b) premature loading (c) uncontrolled heating (d) curing
- The correct step when casting a reinforced member is to ________. (a) remove all spacers before pouring (b) increase water until segregation occurs (c) inspect reinforcement location, formwork and specified cover before placing concrete (d) start stripping formwork before concrete is placed
- Which action does NOT follow sound practice when reading a bond drawing? (a) Treating every drawn half-unit as a full-length stretcher without checking the bond (b) Identifying headers and stretchers on each course (c) Tracing the intended overlap of successive courses (d) Checking corners and returns for continuity
- A foundation design based only on appearance, without checking soil bearing capacity, risks ________. (a) reliable transfer of load under all conditions (b) unequal settlement and cracking (c) eliminating all effects of groundwater (d) making the foundation independent of the structure
- The ________ of a brick is its short end exposed on the face of a wall. (a) stretcher face (b) bed joint (c) perpend (d) header
- Which practice does NOT reduce the risk of failure in a textured render finish? (a) Applying it over an unstable, contaminated or poorly prepared base (b) Following a suitable mixing procedure (c) Observing curing and substrate condition (d) Matching application method to the material
- Which action does NOT protect reinforcement effectiveness? (a) Providing specified concrete cover (b) Maintaining correct steel position (c) Avoiding excessive displacement during compaction (d) Allowing reinforcing bars to remain loose and misplaced during the pour
- ________ is the base preparation typically required before applying an effective plaster finish to a masonry wall. (a) Cleaning and properly preparing the substrate (b) Painting over loose dust (c) Wet-polishing the wall before mortar application (d) Removing sound mortar from all joints
- A wall regularly develops stepped cracks at mortar joints. The defect most directly suggests examining ________. (a) ceiling fan blade width (b) the colour temperature of site lighting (c) support movement, mortar quality and bonding (d) roof drainage alone without examining masonry
- Which of these is not an appropriate response to damp at the base of a new wall? (a) Checking DPC continuity at openings (b) Cutting an uninterrupted path through the installed DPC (c) Examining adjacent ground level and bridging (d) Inspecting construction defects around wall junctions
- In selecting walling units, a key structural consideration is ________. (a) the wall’s intended load and the units’ relevant strength (b) matching every internal wall to a decorative paint colour (c) using identical mortar irrespective of unit type (d) omitting specified wall thickness to conserve space
- The main reason a ceiling may be installed below roof members is to ________. (a) transfer foundation loads directly to soil (b) replace the need for a weatherproof roof covering (c) provide a finished internal surface and accommodate appropriate building services (d) make roof drainage unnecessary
- A masonry project proposes mass concrete for a member carrying substantial bending tension. The decision needs review because ________. (a) plain mass concrete has limited tensile resistance relative to a reinforced solution (b) mass concrete always contains prestressing steel (c) bending can only occur in timber (d) mass concrete is automatically stronger in tension than steel
- Which of these is not an appropriate quality-control observation during concrete placement? (a) Uniform distribution of aggregates (b) Proper consolidation around reinforcement (c) Stable formwork and appropriate placement (d) Visible segregation being accepted as a design feature
- The correct step before estimating tiles from a working drawing is to ________. (a) order a random quantity and omit measurement (b) ignore openings irrespective of their size (c) determine net surface area and tile module, then account for waste and cuts (d) assume all tile sizes cover equal areas
- The ________ of soil indicates the pressure it can sustain without unacceptable failure or settlement. (a) paint absorption (b) tile slip resistance (c) surface reflectance (d) bearing capacity
- Which of these is not a reliable site check on a newly laid wall? (a) Comparing the brick colour with the architect’s clothing (b) Checking plumb with a level or plumb line (c) Checking gauge and joint uniformity (d) Checking the wall line against the drawing
- Which of the following would best improve tile adhesion on a wall? (a) Applying adhesive over loose plaster to save time (b) Cleaning, levelling and preparing the substrate before applying the correct adhesive (c) Laying tiles immediately on a moving crack (d) Ignoring the manufacturer’s setting and curing requirements
- An opening is specified within a load-bearing wall. The drawing must be checked for ________. (a) the manufacturer’s paint advertisement alone (b) the final location of loose furniture (c) the structural support and correct positioning at the opening (d) a reduction in foundation capacity by default
- The main reason floors are selected to suit the intended use is ________. (a) that every building requires an identical surface finish (b) that no floor needs a supporting base (c) that tiles remove the need for structural design (d) that loads, wear and moisture exposure differ by occupancy
- A room floor is 6 m × 4 m and each square tile covers 0.16 m². Ignoring waste, the required number of tiles is ________. (a) 120 (b) 150 (c) 160 (d) 240
- Which of the following best explains the need to consider soil type before constructing a ground floor? (a) Different soils vary in drainage, compressibility and load-bearing behaviour (b) Every soil type behaves identically when saturated (c) Only the colour of soil determines foundation depth (d) Soil assessment is useful solely for wall plastering
- The ________ is the surface treatment used to level or protect masonry with a mortar-based coat. (a) foundation bearing test (b) prestressing tendon (c) plaster or render (d) roof truss
- ________ concrete relies on steel bars to resist significant tensile stresses that plain concrete resists poorly. (a) Mass (b) Reinforced (c) Plain unreinforced (d) Uncompacted
- All the following justify appropriate damp-proofing provisions EXCEPT ________. (a) reducing moisture penetration into masonry (b) protecting interior finishes from damp (c) ensuring rising ground moisture travels freely into wall finishes (d) maintaining continuity across the wall at the required level
- Which positioning of a damp-proof course is most effective against rising moisture? (a) Short pieces placed only at alternate corners (b) A decorative strip applied solely to the external paint (c) A barrier terminated at each doorway without an appropriate detail (d) A continuous barrier in the wall at the specified level with sound junctions
- ________ bond consists of successive courses showing stretchers on the face, with joints staggered between courses. (a) Stack (b) Stretcher (c) English cross (d) Flemish
- A mix that is too wet merely to improve ease of placing may result in ________. (a) automatic improvement in all durability properties (b) no change to hardened concrete quality (c) complete elimination of the need for compaction (d) reduced strength and greater segregation or shrinkage risk
- The correct step immediately after setting out the first course is to ________. (a) apply the final paint finish to uncured masonry (b) check alignment, level and the intended bond before building higher (c) load the wall with heavy roof materials at once (d) omit corner checks if the first course looks straight
- All of these are reasonable tile-laying precautions EXCEPT ________. (a) using uneven joint widths to hide poor setting out (b) checking line and level (c) allowing for cuts at edges (d) using appropriate joint spacing
- Which of these is not a suitable cause of plaster or render failure? (a) Poor bonding to the substrate (b) A sound, properly cleaned and appropriately dampened backing (c) Inappropriate material proportions (d) Premature drying or inadequate curing
- All of the following support sound in-situ concrete production EXCEPT ________. (a) correct proportioning and mixing (b) appropriate placement and compaction (c) suitable curing and protection (d) removing formwork or support before the concrete has adequate strength
- All these operations support sound wall construction EXCEPT ________. (a) setting out to the drawing (b) maintaining specified joint thickness (c) placing consecutive courses with coincident vertical joints throughout (d) checking level and verticality
- ________ refers to the ground material whose bearing characteristics influence the choice of foundation and floor construction. (a) Weathering coat (b) Soil (c) Ceiling lining (d) Tyrolean texture
SECTION B: THEORY (30 Marks)
Instruction: Answer Question 1 and any other TWO questions. Each question carries 10 marks.
1. Answer the following questions.
(a) Analyse five checks that should be made when interpreting a working drawing for a bonded brick wall with a corner return. (5 marks)
(b) A newly erected wall shows aligned joints and out-of-plumb courses. Explain five corrective or preventive site practices. (5 marks)
2. Answer the following questions.
(a) A project site contains variable soil conditions and a ground-floor wall at risk of rising damp. Assess five design or construction implications. (5 marks)
(b) Explain five checks required for correctly detailing a wall opening and its damp-proofing arrangements. (5 marks)
3. Answer the following questions.
(a) A tiler is to cover a wall 5 m by 3 m using tiles covering 0.25 m² each. Calculate the gross tile number without waste and explain the procedure in five scoring stages. (5 marks)
(b) Identify five reasons a tyrolean or Sandtex-type finish may fail or lack durability on masonry. (5 marks)
4. Answer the following questions.
(a) Compare ordinary reinforced concrete with prestressed concrete using five relevant structural or construction distinctions. (5 marks)
(b) Outline five concrete-production precautions from batching to curing for a sound in-situ structural member. (5 marks)
OBJECTIVE MARKING SCHEME
Question 1 – ✅ (d) Internal compression is deliberately introduced before or during service to counter tensile effects
Question 2 – ✅ (c) seek reassessment of the founding conditions before proceeding
Question 3 – ✅ (a) distribute loads and avoid continuous planes of weakness
Question 4 – ✅ (b) Continuous aligned vertical joints through several courses
Question 5 – ✅ (c) introduced compression helps resist service-induced tension and cracking
Question 6 – ✅ (a) 15 m²
Question 7 – ✅ (d) curing
Question 8 – ✅ (c) inspect reinforcement location, formwork and specified cover before placing concrete
Question 9 – ✅ (a) Treating every drawn half-unit as a full-length stretcher without checking the bond
Question 10 – ✅ (b) unequal settlement and cracking
Question 11 – ✅ (d) header
Question 12 – ✅ (a) Applying it over an unstable, contaminated or poorly prepared base
Question 13 – ✅ (d) Allowing reinforcing bars to remain loose and misplaced during the pour
Question 14 – ✅ (a) Cleaning and properly preparing the substrate
Question 15 – ✅ (c) support movement, mortar quality and bonding
Question 16 – ✅ (b) Cutting an uninterrupted path through the installed DPC
Question 17 – ✅ (a) the wall’s intended load and the units’ relevant strength
Question 18 – ✅ (c) provide a finished internal surface and accommodate appropriate building services
Question 19 – ✅ (a) plain mass concrete has limited tensile resistance relative to a reinforced solution
Question 20 – ✅ (d) Visible segregation being accepted as a design feature
Question 21 – ✅ (c) determine net surface area and tile module, then account for waste and cuts
Question 22 – ✅ (d) bearing capacity
Question 23 – ✅ (a) Comparing the brick colour with the architect’s clothing
Question 24 – ✅ (b) Cleaning, levelling and preparing the substrate before applying the correct adhesive
Question 25 – ✅ (c) the structural support and correct positioning at the opening
Question 26 – ✅ (d) that loads, wear and moisture exposure differ by occupancy
Question 27 – ✅ (b) 150
Question 28 – ✅ (a) Different soils vary in drainage, compressibility and load-bearing behaviour
Question 29 – ✅ (c) plaster or render
Question 30 – ✅ (b) Reinforced
Question 31 – ✅ (c) ensuring rising ground moisture travels freely into wall finishes
Question 32 – ✅ (d) A continuous barrier in the wall at the specified level with sound junctions
Question 33 – ✅ (b) Stretcher
Question 34 – ✅ (d) reduced strength and greater segregation or shrinkage risk
Question 35 – ✅ (b) check alignment, level and the intended bond before building higher
Question 36 – ✅ (a) using uneven joint widths to hide poor setting out
Question 37 – ✅ (b) A sound, properly cleaned and appropriately dampened backing
Question 38 – ✅ (d) removing formwork or support before the concrete has adequate strength
Question 39 – ✅ (c) placing consecutive courses with coincident vertical joints throughout
Question 40 – ✅ (b) Soil
THEORY MARKING SCHEME (Answer 3 × 10 = 30 Marks)
Question 1 (10 Marks)
(a) 5 marks: Identify bond type (1); course overlap (1); headers/stretchers correctly placed (1); specified dimensions and thickness (1); corners/returns and opening details (1).
(b) 5 marks: Correct setting out (1); stagger joints (1); check plumb (1); check level (1); control joint thickness and line/quality (1).
Question 2 (10 Marks)
(a) 5 marks: Assess bearing capacity (1); settlement risk (1); drainage/moisture (1); suitable floor or foundation construction (1); continuous appropriately positioned DPC (1).
(b) 5 marks: Review drawing and dimensions (1); structural support at opening (1); DPC level (1); continuity at junctions (1); check bridging/adjacent ground levels (1).
Question 3 (10 Marks)
(a) 5 marks: Wall area = 5 × 3 = 15 m² (2); tile area 0.25 m² (1); number = 15/0.25 (1); result 60 (1).
(b) 5 marks: Poor surface preparation (1); loose/unstable base (1); incorrect mixing or product use (1); incompatible application/conditions (1); inadequate curing or drying control (1).
Question 4 (10 Marks)
(a) 5 marks: Reinforced steel action (1); deliberate compressive prestress (1); tendon/steel arrangement (1); service crack/deflection control (1); suitability for spans or loading (1).
(b) 5 marks: Correct materials/proportions (1); mixing (1); secure formwork/rebar cover (1); careful placing/compaction (1); moisture/temperature curing (1).